We checked the wiring, power, lights, data and coax, security, - all appears to be in place.
The final coat of STO colour was being applied to the plaster finish. Some of the Stria board on the top level had been applied. The colours are looking good.
More than half of the linings to the upstairs had been fitted. Mark, the carpenter, thinks he will have the linings finished by the end of the next week. There could be a delay as the heat pump cassette has not arrived and must be fitted before the ceiling lining.
The shower units were on site and the upstairs unit has some damage.
| Wing Lounge Bathroom wall |
| View of Kitchen thru Gallery wall |
| Bedroom 3 |