The concrete floor was poured on Monday (1 Oct) and on Friday (05 Oct) the first frames were stood up. We traveled to Havelock North on Friday and arrived to see the frames for the main part of the house were up. Later that day the frames on the East Wing were stood up.
Next to do is install the steel posts and beams over the garage to support the upper story and build the sub floor. We expect that to be done next week.
Photo taken by Scott of the first frames going up.
Midday Friday - what can be seen from the lounge
Timeline 05 Oct 2012 early afternoon
Timeline 05 Oct 2012 - completed end of day
View from Driveway
We traveled back to Wellington after taking these pics.