On this day (26 April 2013) Jono started boxing up the patio while a bobcat was scraping where the drive is to be laid. Early next week the patio will be poured and later in the week the driveway.
The electrical is 40% complete with most of the fittings installed. The central wiring is yet to be started. By the end of the week we expect most of the wiring will be finished. Chubb have started the fitout of the alarm system, work on the CCTV has not started and a decision is to be made on the products to instal.
Later in the day the floors were swept in readiness for carpet. Carpet will also be installed during the week. The garage door is also
Outstanding is: gas line and meter, power and telecom cables connected. Until these are completed the driveway and some concrete cannot be laid.